INTERPRETATION AND ANALYSIS OF THE FLOW CHART OF THE process "DEFINITION
OF THE PROJECT ACTIVITIES"
INTRODUCTION
The purpose of
this work is to describe in detail the
Inputs, Tools and Techniques, and Outputs of the process 6.2 Define Project
Activities, that corresponds to the Area of Knowledge "Project Time
Management" of the PMBOK, indicating in a reasoned way, the best use
of all its elements.
Likewise, a
critical analysis of the exposed descriptions of the process and the respective
conclusions on its relevance for the development of the Knowledge Area
"Project Time Management" and the project in general are presented.
Process
Description 6.2: Define Project activities
Process definition
Defining the
Activities is the process that consists of identifying the specific actions to
be carried out to prepare the project deliverables. The actions to be
developed are represented as activities, meaning as activity every part of the work to be done in the
course of a project. The 5.4 Create the
WBS process identifies the deliverables at the lowest level of the work
breakdown structure (WBS), called work packages. From the work
packages originates the decomposition into smaller components
called activities; The set of activities that are obtained from the
decomposition of a work package, represent all the actions that
must be carried out to complete the respective work
package. The activities provide the basis for estimating,
planning, executing, monitoring and controlling the project work in all
other knowledge areas.
Process Flow
Diagram 6.2 Define Activities
Define the Activities
of the Project: Inputs
1. Scope
Baseline: The Scope Baseline comes from process 5.4
Create the WBS. It is one of the components of the Management Plan of the
Project, and it is comprised of the following elements:
·
Project Scope Statement
·
The WBS (Work Breakdown Structure)
·
The EDT Dictionary
This document is
very important in defining activities, since it is from the level of
breakdown into work packages that activities can be identified.
2. Environmental Factors of the Company: Among the
environmental factors of the company that can influence the process 6.2 Define
the Activities, is the project management information system or
the project management software used by the company or organization to manage
projects (e.g .: MS-Project).
3. Organizational Process
Assets: Organizational process assets that can
influence the process 6.2 Define Activities include, but
are not limited to:
·
Existing policies, procedures and guidelines, whether
formal or informal, related to the planning of activities.
·
The knowledge base of lessons learned.
· These two aspects refer, in the first place, to
regulations or internal procedures of the organization commonly used in the
planning of project activities. Some companies have them, others not. Secondly,
the knowledge base of lessons learned relate to a historical background
from previous projects developed by the organization. This
information is important for process 6.2, since the historical files
have detailed information on similar works successfully completed, so this
experience facilitates the identification of the elements and activities of a
new project.
4.
Process 6.1 Plan
Schedule Management. This process included in PMBOK v.5 is considered now
a previous step for the definition of activities and all subsequent processes.
The key input from the schedule management plan is the prescribed level of detail
needed to manage the work of the whole project.
Define Project Activities:
Tools and Techniques
1. Decomposition: The
decomposition technique, as applied to define activities, consists of subdividing
the project work packages into smaller and easier-to-manage components, called
activities.
2. Gradual Planning: Gradual planning is a form of gradual elaboration planning,
where work to be developed in the short term is planned in detail and future
work is planned at a higher level of the WBS. It is about progressive
planning.
3. Templates: A template is
a list of standard activities or part of a project listed above, which can
be used as reference to develop the list of activities of a
new project.
4. Expert Judgment: Members of the
project team or other experts with experience and skills in developing detailed
project scope statements, WBS, and project schedules, can contribute with
their expertise to define activities.
Define Project Activities:
Outputs
- List of Activities: It is the main output of the process and consists of an exhaustive list that includes all the activities of the schedule of the different work packages, necessary for the execution of the project. The activity list includes the activity identifier and a description of the scope of work for each activity.
- Activity Attributes: Activity attributes expand the definition of the activity, and include: the activity identifier, the WBS identifier and the activity name, the activity codes, the activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions. Durations, costs and resources are determined in other processes.
- Milestones List: A milestone is a significant point or event within the project. Unlike an activity, it does not consume resources or has no duration. Milestones can be required or optional, such as those based on historical information.
My own analysis of the process 6.2 Define Activities
Inputs
The Process Flow Diagram indicates that the main
input, without which this process cannot be developed, is the Scope
Baseline, represented by the WBS obtained from 5.4 Create the WBS. The
remaining input elements may or may not exist.
Tools and
Techniques
With regard to Tools and Techniques, the ideal is
to apply “a little bit of everything”; but both the decomposition
technique and the gradual planning technique require a high
component of Expert Judgment. The previous experience in projects, of
people belonging to the project team or interested parties with high technical
expertise, is decisive for obtaining quality outputs from this
process. Finally, by way of observation, it is worth mentioning that the
PMBOK v.5 indicates in paragraph 6.2.2.1 Decomposition, that the WBS
and the List of Activities can be developed simultaneously. If this is the
case, the WBS is subject to be modified, so there must be an exit from the
6.2 process in the form of Updating the Project Documents that represents
the update / modification of the WBS.
Outputs
In my opinion, the three first outputs of the process could
be included in a single list called "List of Activities and
Milestones". The attributes are inherent to the activities, so that I
find it unmeaningful to generate two lists, one with activities and one with
attributes, which can even have repeated elements. Milestones can be
presented separately in another list or included in the activity list with
a special identification. In the definitive list of activities in the
schedule, milestones are recognized as having zero duration “0” and the project
planning software identifies them in a special way. All the outputs of
this process are inputs of other processes of the same Knowledge Area (Project
Time Management)
No hay comentarios.:
Publicar un comentario